The electricity grid is becoming a critical constraint for warehouse development, writes George Day (pictured below), senior project manager at Pulse Consult.
Complex regulations, lengthy approval timelines and environmental impacts have long made planning a major hurdle for warehousing developers. Yet a new, critical constraint is taking centre stage: power.
Set against a background of increasing competition for grid capacity, Ofgem has launched a consultation as part of a wider programme of reforms to ensure network capacity is used for the projects that need it most, sending a clear message that grid capacity and connection delays are emerging as a critical and increasingly decisive risk to viable delivery.
In 2026, over 80% of UK logistics occupiers expect that their power requirements will increase over the next 12 months as more is needed to support large-scale, power-hungry sites. As a result, power availability is moving from a tick-box exercise to an integral requirement for modern warehouse development.
To stay ahead of the power challenge, developers must move from reacting to grid constraints to anticipating them, making power availability a fundamental consideration from the outset. This means undertaking early due diligence, engaging with key stakeholders and working collaboratively to identify constraints.
Preparing for a tech-intensive future
It isn’t surprising that the issue of power is being pushed to the top of the agenda. The warehouse of tomorrow is becoming increasingly more tech-intensive, from automated systems and substantial refrigeration demands to the electrification of fleets. As these requirements and advancements evolve, the technology required to support them can increase over the lifetime of a facility, causing unanticipated costs.
Developers need to look beyond the power required to get a project operational on day one and, rather, consider its ultimate power capacity from the outset. Failing to consider this growth can leave projects constrained by original grid connections, requiring costly upgrades later down the line. To future-proof power capacity, grid considerations need to be treated as two-fold. Not only do project teams need to ensure there is sufficient capacity to meet immediate operational requirements, but they must also anticipate the future needs of the building and its occupiers.

Power is no longer a simple utility. It is becoming a core determinant of the viability of a project. Answering early on the important questions of where, how and at what cost will bolster project resilience and give greater certainty and control over both project costs and the delivery path.
Act now for long-term project resilience
The complex planning process and the challenge of grid capacity are intrinsically linked, with site selection now requiring developers to consider not only whether land is suitable for development, but whether it can also secure the power needed to support it.
Those that fail to recognise this are forced to engage unexpectedly with Distribution Network Operators (DNOs) to install the relevant grid connections. This engagement can introduce significant delays and unexpected costs, with connection assessments, timelines and deliverability all placing constraints on initial project plans.
Data from Ofgem gathered as part of a feedback initiative reflects a clear message: grid connection delays are occurring too often, and delivery milestones are therefore being missed. For developers, the consequence of this is a domino effect, creating knock-on delays and increasing costs that place project viability at risk.
To mitigate this issue of squeezed DNOs and power-heavy projects, early due diligence is critical and should be integrated into the planning process, long before spades hit the ground. By introducing stringent due diligence teams to identify appropriate land that can support the power requirements needed, teams can uncover grid constraints early, reducing costly delays and increasing confidence in project deliverability.
Powering progress across every workstream
Early due diligence must be matched by early engagement and collaboration between key project partners, ensuring power constraints are understood and addressed before they become a barrier to delivery.
Project management teams should bring together key stakeholders from the outset to identify the key considerations that must be addressed early on, ensuring project viability later down the line. With this comes an integral reordering of priorities: power cannot sit at the end of the tick list. Instead, it must be mapped into the critical path from the outset, ensuring that key project stakeholders have the right discussions at the right time to determine where grid constraints sit within the wider delivery programme.
However, although project management teams can be the driver of these discussions, power supply considerations need to be embedded across entire development teams, rather than considered in a single workstream. From planning and commercial services to design and project controls teams, all functions need visibility of power requirements and potential constraints, ensuring that decisions are aligned.
The objective of early engagement is not simply to start conversations sooner, but to bring forward decisions that could otherwise become barriers to delivery.
Staying ahead of the power curve
The warehousing and logistics sector is becoming more technologically advanced, with greater reliance on sophisticated power-intensive systems. With this comes the certainty that power requirements and the reliance on sufficient grid connections are likely to continue evolving.
But with power becoming an increasingly constrained resource, project teams need to stay ahead of the curve and anticipate where grid capacity issues may arise, understanding how this may affect grid availability and project viability later down the line. Those that anticipate rising power demand and plan for it early will be better positioned to control costs, protect delivery timelines and ultimately turn power availability into a project advantage.